DEALING WITH CONSTRUCTION PERMITS

Ministry of Public Works and Transport has revised construction management regulations which are enacted in January 2019. These regulations shortened number of procedures and eliminated some irrelevant and repetitive documents for getting construction permits. The regulations will also impose time limits for dealing with construction permits.

2.1

 

Published regulation, brochure and poster for providing information for those apply for construction permits in April 2019.

(Pursuant to the agreement of Minister on construction management, No 2241/mpwt, dated 31 January 2019)

2.2

Shortened procedures for obtaining construction permits from 11 to 7 and spent time no more than 30 days

2.3

Application forms for Construction Permits can be downloaded from

https://www.mpwt.gov.la